Van Wyck Expressway Capacity And Access Improvements To Jfk Airport

Scope of Work
  • Micropile Installation for Bridge Abutments and Piers
  • Drilled Shaft Installation for Retaining Wall and Noise Barrier
  • Water Treatment
Customer
Tully Construction Co., Inc.

Techniques

New York State Department of Transportation (NYSDOT)

Van Wyck Expressway Capacity And Access Improvements To Jfk Airport

The Project

The project will increase the Van Wyck Expressway capacity between the Kew Gardens Interchange and JFK Airport. It will also address operational, geometric, and structural deficiencies on the expressway.

The Solution

As of October 2023, Tri-State has reached about the halfway point of the micropile and drilled-shaft scope after installing more than 150 micropiles to support the new bridge abutments and sewer structures and drilling hundreds of drilled-shaft locations for the new retaining wall and noise barriers. We have also successfully performed six high-capacity verification load tests and six proof load tests.

The Challenge

Some challenges include creating the bond zone in dense sand and working closely with the general contractor, their consultant, and NYSDOT to meet the tight project schedule.

Project Facts

Owner(s)

New York State Department of Transportation (NYSDOT)
Design Consultant
STV
Budget