

Project at a Glance
Owner: NYS Department of Transportation
Client: Halmar International
Location: Mamaroneck NY
Work Type: Bypass Pumping
Project Overview
Tri-State Civil Construction was selected by Halmar International to provide the temporary bypass pumping system required for the replacement of an existing 66-inch sanitary sewer crossing beneath the U.S. Route 1 Bridge over the Mamaroneck River. The work was performed as part of the NYSDOT Lower Westchester Bridge Bundle Design-Build Project, a major infrastructure initiative focused on improving flood resiliency, replacing aging bridges, and modernizing critical utilities throughout Westchester County.
The bypass system allowed the existing sewer to remain fully operational while the original crossing was removed and replaced, ensuring uninterrupted wastewater service to the surrounding community throughout construction.
Scope of Work
Tri-State furnished a complete turnkey bypass pumping system, including engineering support, temporary pumping equipment, HDPE bypass piping, installation, operation, maintenance, monitoring, and final system removal.
Working within a dense urban environment adjacent to the Mamaroneck River presented significant logistical challenges. The bypass system was installed while maintaining traffic along Route 1, protecting nearby businesses and residences, and coordinating with multiple ongoing construction activities.
Throughout the duration of the project, Tri-State maintained continuous operation of the temporary pumping system, providing around-the-clock monitoring and rapid response capability to ensure uninterrupted service and safe project execution.


Project Challenges
This project required careful planning and execution due to several unique site constraints:
· Maintaining continuous operation of an active 66-inch sewer.
· Construction adjacent to the tidal Mamaroneck River.
· Limited working space within a busy downtown corridor.
· Coordination with bridge construction, utility relocation, and roadway improvements.
· Maintaining public safety and minimizing disruption to traffic and nearby businesses.
· Delivering a highly reliable bypass system with redundant pumping capacity.
Results
The bypass pumping operation successfully maintained uninterrupted sewer service throughout construction, allowing Halmar International to complete the replacement of the 66-inch sewer crossing while advancing one of New York's most significant transportation resiliency projects.
The successful completion of this work demonstrates Tri-State Civil Construction's ability to design, install, and operate complex bypass pumping systems for critical municipal infrastructure projects where reliability, safety, and continuous operation are essential.
· Complete turnkey bypass pumping system
· Continuous operation of an active 66-inch sewer
· Temporary HDPE bypass pipeline installation
· 24/7 system monitoring and maintenance
· Zero interruption of sewer service during construction
· Performed as part of NYSDOT's award-winning Lower Westchester Bridge Bundle Design-Build Project






