Project at a Glance
Owner: NYS Department of Desing and Construction
Client: Tutor Perini
Location: Brooklyn, NY
Work Type: Soldier Piles and Lagging Wall
Project Overview
Tri-State Civil Construction was selected by Tutor Perini to perform the complete field installation and testing operations for more than 70 tiebacks, as part of the support-of-excavation work for the Brooklyn Jail Facility at 275 Atlantic Avenue.
Tri-State mobilized and completed drilling and installation of all assigned tiebacks within the same month. Using a Comacchio MC-14 drill rig, the crew installed the anchors through sandy subsurface conditions and performed all associated field operations, including drilling, causing
advancement, anchor installation, grouting, testing, and lock-off.
The work was performed within a constrained urban site surrounded by active streets, existing utilities, and nearby NYCT infrastructure. The project required careful coordination and experienced equipment operation to complete the tiebacks safely while limiting impacts to surrounding facilities. The project drawings included extensive monitoring requirements for nearby buildings, support-of-excavation elements, and NYCT structures.
Scope of Work
Tri-State furnished a complete tieback installation for all assigned tiebacks at Brooklyn Jail Facility. This installation included associated field operations, extensive monitoring of nearby buildings, drilling, casing advancement, anchor installation, grouting, testing, lock-off, and an experienced field team.
Working withing the constrained urban site required careful coordination and experienced equipment operation. Tiebacks required safe installation while limiting impacts to surrounding facilities and existing utilities.
Throughout the project duration, Tri-State subsequently completed testing of all installed tiebacks. The experienced field team provided the additional operational support needed to maintain and improve the project schedule, successfully completed all required anchor testing, and finished its work without a safety incident.


Project Challenges
This project required careful planning and execution due to several unique site constraints:
- Limited working space within a busy downtown corridor.
- Extensive monitoring requirements for adjacent buildings.
- Managed and prevented unforeseen site conditions.
- Coordination with field team to maintain and improve project schedule.
- Maintaining public safety and minimizing disruption to traffic and nearby businesses.
- Completed work without a safety incident.
Results
Tieback operation successfully maintained soil stability, monitoring and installation process throughout construction, allowing Tutor Perini to continue their ongoing process of Borough-Based Jail new construction and site SOE work pertaining to the basement and any utilities needed. This project helped advance New York’s most innovative institutional facility.
The completion of this work demonstrates Tri-State Civil Construction’s ability to install, monitor, and efficiently implement potent tieback systems for critical social infrastructure projects where safety, reputation, and a reliable process are essential.
- Complete Borough-Based Jail tieback system.
- Continuous monitoring of surrounding infrastructure and utilities.
- Work in constrained urban site with active streets
- Successful completion of all required anchoring testing.
- Finished work without any safety incidents.
- Performed as part of NYCDDC’s innovative institutional faculty.