Project at a Glance
- Client: EE Cruz & Company, Inc.
- Owner: New York City Transit Authority
- Location: Forsyth Street, New York, NY
- Tri-State Scope: Dewatering (Deep Wells)
- Our Timeline: January 2022 - 2022
Scope
NYCTA Contract E-31699 was issued to install a new Emergency Vent Plant for the 6th Ave Line on Forsyth Street between Delancey Street and Rivington Street in Manhattan, NY.
Tri-State Work Summary
To assist the GC with their excavation, Tri-State designed, installed, and implemented a dewatering plan consisting of 12 Deep Wells at the project site. The Deep Wells were installed to 50-60’ depth to ensure a dry and safe excavation area after obtaining applicable dewatering permits.
Excavations for the Emergency Vent Plant project took place on a busy street in lower Manhattan, NY. Since the project was required to progress in any way possible, the General Contractor prioritized excavation prior to full installation and implementation of the dewatering system. Tri-State successfully installed the dewatering system within the project site, above sub-grade, to alleviate the already tight working conditions on site. In order to facilitate the installation properly, Tri-State provided and required proper PPE, specifically Fall Protection/Arrest systems to install the header system to hang from the SOE.
The work for the Emergency Vent Plant project was conducted throughout the months of January to current day of May 2022. Despite the continuing challenges of the COVID-19 Pandemic, Tri-State maintains operations for the project at hand while strictly adhering to CDC guidelines and taking precautions to act against the spread of COVID-19.